Non-Stop Bridge Assembly Instructions


Non-Stop Bridge Assembly Instructions




1. Install Wall Side Truss.





Be sure the ends are locked as shown above.





2. Mate the Middle Section to the Wall-Side Truss.





3. Put one end of the Laborers-Side Truss in place, then hang the other end as you mate it to the Middle Section





4. Install Spacers and Straight Braces for diagonal bracing, as shown in the completed structure above.


Maximum safe loading capacity of Non-Stop Scaffolding: 3000 pounds in every other bay. Each bridge counts as one bay.




5. Install standard 81-inch Non-Stop cut-boards on the wall side.

Note: To lower the work platfom when a bridge is installed, shift winches to low gear.